Electrification Of Manza Dispensary

Ongoing GoMC-PMTS-2026-8927
Budget & Expenditure
Approved
KES 1.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Components (1)
Component Budget Expenditure Status
CONSTRUCTION OF PIT LATRINE AT MANZA DISP KES 1.00M KES 0.00 Null
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2026-8927
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2025/2026
  • SourceSelect funds source
  • Funded FromHeadquaters
  • CategoryNon Flagship
  • Start21 Dec 2025
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 13 Oct 2025
Approved Requisition
Phase Two · 21 Oct 2025
Floated
Phase Two · 30 Oct 2025
Awarded
Phase Two · 12 Dec 2025
Site Handover
Phase Three · 03 Jan 2026
Not Started
Phase Three · 03 Jan 2026
Ongoing
Phase Three · 09 Jan 2026