Completion Of Modern Lab Block at Kathonzweni Health Centre

Ongoing Flagship GoMC-PMTS-2026-2349
Budget & Expenditure
Approved
KES 2.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2026-2349
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2025/2026
  • SourceSelect funds source
  • Funded FromHeadquaters
  • CategoryFlagship
  • Start03 Jan 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 12 Oct 2025
Approved Requisition
Phase Two · 21 Oct 2025
Floated
Phase Two · 30 Oct 2025
Awarded
Phase Two · 11 Dec 2025
Site Handover
Phase Three · 12 Jan 2026
Not Started
Phase Three · 12 Jan 2026
Ongoing
Phase Three · 25 Jan 2026