Rehabilitation Of Kaiti 1 Filtration Unit & Pipeline

Completed GoMC-PMTS-2026-5093
Project Description
Rehabilitation of Kaiti 1 filtration unit & pipeline
Budget & Expenditure
Approved
KES 3.14M
Contract
KES 0.00
Spent
KES 3.14M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2026-5093
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Finance, Planning, Budget and Revenu
  • DirectorateAdministration
  • FY2025/2026
  • SourceEmergency fund
  • Funded FromHeadquaters
  • CategoryNon Flagship
  • Start04 May 2026
  • End30 Jul 2026
Timeline
Cabinet Paper Approved
Phase One · 07 Apr 2026
Approved Requisition
Phase Two · 14 Apr 2026
Floated
Phase Two · 14 Apr 2026
Awarded
Phase Two · 04 May 2026
Site Handover
Phase Three · 12 May 2026
Not Started
Phase Three · 12 May 2026
Ongoing
Phase Three · 13 May 2026
Completed
Phase Three · 26 Jun 2026