Equipping Of Muthungue Borehole

Completed GoMC-PMTS-2026-2684
Project Description

Borehole equipping with solar system 

Budget & Expenditure
Approved
KES 2.25M
Contract
KES 0.00
Spent
KES 2.13M
Utilisation
94.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2026-2684
  • WardThange
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Mar 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 26 Jan 2026
Approved Requisition
Phase Two · 29 Jan 2026
Floated
Phase Two · 10 Feb 2026
Awarded
Phase Two · 10 Mar 2026
Site Handover
Phase Three · 16 Mar 2026
Not Started
Phase Three · 16 Mar 2026
Ongoing
Phase Three · 18 Jun 2026
Completed
Phase Three · 30 May 2026