Matiliku/ Kwa Kasoda Tanks

Completed GoMC-PMTS-2026-2257
Project Description

Supply of 10000l water tank & construction of tank platform at Matiliku kwa Kasoda

Budget & Expenditure
Approved
KES 299.9K
Contract
KES 0.00
Spent
KES 299.9K
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2026-2257
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromHeadquaters
  • CategoryNon Flagship
  • Start25 May 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 02 Mar 2026
Approved Requisition
Phase Two · 10 Mar 2026
Floated
Phase Two · 15 Apr 2026
Awarded
Phase Two · 22 May 2026
Site Handover
Phase Three · 05 Jun 2026
Not Started
Phase Three · 08 Jun 2026
Ongoing
Phase Three · 08 Jun 2026
Completed
Phase Three · 30 May 2026