Road Improvement Programme in Nguu Masumba through -nys/mtf

Ongoing GoMC-PMTS-2025-4918
Project Description
Road opening and grading-NYS/MTF


Budget & Expenditure
Approved
KES 2.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4918
  • WardNguu/Masumba
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start05 Jan 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2025
Approved Requisition
Phase Two · 18 Dec 2025
Floated
Phase Two · 30 Jan 2026
Floated
Phase Two · 30 Jan 2026
Awarded
Phase Two · 17 Dec 2025
Site Handover
Phase Three · 05 Jan 2026
Not Started
Phase Three · 05 Jan 2026
Ongoing
Phase Three · 05 Jan 2026