Road Structures At Wito Farm-mbavani-kaiani- Sinai Road

Completed GoMC-PMTS-2025-5434
Project Description

Road structures at Wito farm-Mbavani-Kaiani- Sinai road

Budget & Expenditure
Approved
KES 1.70M
Contract
KES 1.58M
Spent
KES 1.58M
Utilisation
93.1%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-5434
  • WardMavindini
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start09 Mar 2026
  • End30 Jul 2026
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2025
Approved Requisition
Phase Two · 10 Dec 2025
Floated
Phase Two · 30 Jan 2026
Awarded
Phase Two · 03 Mar 2026
Site Handover
Phase Three · 16 Mar 2026
Not Started
Phase Three · 16 Mar 2026
Ongoing
Phase Three · 20 Mar 2026
Completed
Phase Three · 08 May 2026