Construction of kwa Malong'a Sand Dam

Ongoing GoMC-PMTS-2025-4126
Project Description
  • Site cllearance 
  • Backfiling 
  • Murraming 
  • Gabion works
  • Stone pitching 
  • Culverts - 12
Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4126
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateMakueni County Sand Conservation and Utilization Authority
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start19 Jun 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 29 Jan 2026
Approved Requisition
Phase Two · 02 Feb 2026
Floated
Phase Two · 13 May 2026
Awarded
Phase Two · 08 Jun 2026
Site Handover
Phase Three · 18 Jun 2026
Not Started
Phase Three · 18 Jun 2026
Ongoing
Phase Three · 19 Jun 2026