Fencing And Roofing Of Water Tanks In Emali Business Center

Ongoing GoMC-PMTS-2025-5633
Project Description

Fencing of 4 water tanks at;

  1. Opposite Revenue Office - 8 tanks on a concrete slab
  2. Adjacent to the garbage transfer point- 8 ground placed tanks
  3. Near Emali Business park public toilets - 8 tanks on a slab 
  4. Next to vegetable market shade- 2 tanks 
Budget & Expenditure
Approved
KES 2.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Gallery (2 photos)
Fencing Of The Water Tanks
Fencing Of The Water Tanks
Signange
Signange
Citizen Feedback
18 Aug 2026
WIZI TUPU

How does an installation of these grills add to 2m??? Mutula tunakuona sana ......

Project Details
  • RefGoMC-PMTS-2025-5633
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateEmali/Sultan Hamud Municipality
  • FY2025/2026
  • SourceExchequer
  • Funded FromHeadquaters
  • CategoryNon Flagship
  • Start09 Mar 2026
  • End29 May 2026
Timeline
Cabinet Paper Approved
Phase One · 22 Jul 2025
Approved Requisition
Phase Two · 06 Oct 2025
Floated
Phase Two · 28 Nov 2025
Awarded
Phase Two · 09 Feb 2026
Site Handover
Phase Three · 09 Mar 2026
Not Started
Phase Three · 09 Mar 2026
Ongoing
Phase Three · 09 Mar 2026