Kwa Koki,isololo Water Project

Completed GoMC-PMTS-2025-9550
Project Description
Kwa koki,isololo water project
Budget & Expenditure
Approved
KES 500.0K
Contract
KES 0.00
Spent
KES 477.0K
Utilisation
95.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-9550
  • WardNzaui/Kilili/Kalamba
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start04 May 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 02 Mar 2026
Approved Requisition
Phase Two · 20 Apr 2026
Floated
Phase Two · 23 Apr 2026
Awarded
Phase Two · 30 Apr 2026
Site Handover
Phase Three · 07 May 2026
Not Started
Phase Three · 07 May 2026
Ongoing
Phase Three · 11 May 2026
Completed
Phase Three · 23 Jun 2026