Nduu water project

Completed GoMC-PMTS-2025-4711
Project Description
Nduu Water Project -Construction of Sump tank, Raising the weir, pump set, Rehabilitation of Kwa Ndeke rising main distribution line and return line.
Budget & Expenditure
Approved
KES 2.00M
Contract
KES 0.00
Spent
KES 1.85M
Utilisation
92.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4711
  • WardKilungu
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start14 May 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 03 May 2026
Approved Requisition
Phase Two · 05 May 2026
Floated
Phase Two · 12 May 2026
Awarded
Phase Two · 15 May 2026
Site Handover
Phase Three · 18 May 2026
Not Started
Phase Three · 18 May 2026
Ongoing
Phase Three · 18 May 2026
Completed
Phase Three · 30 Jun 2026