Kitise Water Project - Upgrading Of 3

Completed GoMC-PMTS-2025-4867
Project Description
Kitise water project - Upgrading of 3" rising main
Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 8.61M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4867
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromHeadquaters
  • CategoryNon Flagship
  • Start04 May 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 18 Apr 2026
Approved Requisition
Phase Two · 20 Apr 2026
Floated
Phase Two · 23 Apr 2026
Awarded
Phase Two · 30 Apr 2026
Site Handover
Phase Three · 04 May 2026
Not Started
Phase Three · 04 May 2026
Ongoing
Phase Three · 04 May 2026
Completed
Phase Three · 25 Jun 2026